Clarifications

There are 129 clarifications for this DPS

50. Are buyers able to filter suppliers, or do they only filter services they require?
CCS can confirm the customers can use the DPS Services Matrix filters to select either one or a combination of services from each of distinct service categories based on their individual customer requirements.
Answered
09/11/2018 14:48
49. At which stage of the SQ do you select the relevant Services that our organisation can provide in line with HELGA requirements?
The Selection Questionnaire is divided into two parts, SQ and DPSQ. The DPSQ is the section where organisations are required to select their services offering. Please refer to the bid pack 'SQ HELGA PDF v1', this provides you with a PDF copy of all the questions contained within the online electronic complete Selection Questionnaire (SQ/ DPSQ). Once you have accessed the PDF, select 'DPS Profile HELGA v1' from the book mark list, this will enable you to view the complete DPSQ which details the service offering specific questions.
Answered
09/11/2018 14:47
48. Re Q129 - Can you direct us to the information on "minimum financial threshold" in the "evaluation criteria". Where are these evaluation criteria to be found.
Please refer to the DPS Needs document which forms part of the bid pack, point 28 (a) Table A - Financial Assessment Matrix, which forms part of the bid pack for RM3824 HELGA DPS. In the event that a bidder fails the D&B failure scores detailed as above, CCS will undertake the necessary steps in accordance with points 26 - 34 of the DPS Needs document to further assess a bidders financial status.
Answered
08/11/2018 09:27
47. Can we add sub-contractors after successfully joining the DPS?
Suppliers should list all known sub-contractors as detailed in DPS Schedule 7 (Sub-Contractors) of the DPS Agreement which forms part of the RM3824 bid pack. Suppliers are able to use different sub-contractors during the lifetime of their DPS Agreement, however any changes to sub contracting arrangements are subject to the obligations under clause 25.1 (Appointment of Sub-Contractors).
Answered
06/11/2018 14:19
46. Can we edit our submission once qualified and live on the DPS?
CCS can confirm that suppliers can update their service offering (filter selection) as detailed in Attachment 1 - RM3824 HELGA Filters Matrix only once appointed to the DPS. For further information regarding how to update answers, please refer to the DPS Needs document 'Updating Answers in the Selection Questionnaire, Dynamic Purchasing System Questionnaire (DPSQ)' section (points 69 - 83) which forms part of the bid pack.
Answered
06/11/2018 14:15
45. How should the PSC (Persons with Significant Control Question be answered where individuals are PSCs by virtue of their board membership rather than shareholding. We have two PSCs by virtue of board membership which we have not declared on the SQ since if 'Yes' is answered to the PSC question, the only options provided are for persons with shareholdings of 25% or more.
CCS can confirm responses are only required for Persons with Significant Control (PSC) with shareholdings of 25% or more, board membership confirmation is not required.
Answered
06/11/2018 14:08
44. Section 52 in the Helga 'Read First' document makes reference to involvement in multiple bids We have submitted an SQ as a single entity. Can you take us through the process if we wish to also lead a Helga submission which involves other companies? I have assumed that we would initiate a separate from our own company (this time as a lead company), but on the website it does not seem possible to commence a new Helga SQ by the same company as an existing one. Can you clarify?
CCS can confirm that your organisation can only act as a 'lead' bidder for one SQ submission for RM3824. As you have confirmed that your organisation has submitted an SQ as a single legal entity (lead), your organisation would not be able to apply as a lead bidder for a separate submission for a group of economic operators or as a member of that group.
Answered
06/11/2018 14:04
42. Schedule 14 Insurance Requirements, Annex 1, Part B Professional Indemnity Insurance, Clause 8.1 stipulates a Maximum deductible threshold - "to be agreed with Supplier". The level of our excess on PI Insurance is confidential, and therefore cannot be disclosed. Can CCS please confirm this is acceptable?
CCS can confirm that appointed suppliers to the RM3824 HELGA DPS, may be required to confirm their maximum deductible threshold if requested by CCS at any point during the lifetime of the DPS Agreement.
Answered
06/11/2018 13:55
41. On the DPS questionnaire it requests I Q21/22 to name subcontractors. We carry out our core services in house, however specialist services we will utilise our supply chain partners, however these will be unknown as will be dependent on the location , type and scope of services required. Can you advise how we answer this, is there a further opportunity in the call for competition to add these?
CCS does not require all sub-contractors to be disclosed. You need only disclose any known sub-contractors who directly contribute to your ability to meet your obligations under the DPS Agreement (including under any Contract), regardless of size as there is no minimum size of sub-contractor. Furthermore, there is no requirement to specify sub-contractors supplying general services to you (such as window cleaners etc.) that only indirectly enable you to perform the DPS Agreement.
Answered
02/11/2018 12:15
40. The link within Appendix 2b takes you to the contract notice, not the contract terms?
Please refer to the Attachments within the link provided which details the Contract Terms for RM3824 HELGA DPS.
Answered
02/11/2018 12:08
39. I would like some help with answering the question associated with contractual obligations assigned to the sub-contractor. How do I accurately identify the correct percentage to use? I have a subcontractor providing CHP services to a district heat network. The contractual obligations for this part of the contract will be 95% assigned to this subcontractor. However, they will not be assigned any other obligations. CHP obligations could be 10% of the total obligations within the overall contract. Should I submit 10% or 95%.
CCS can confirm the overall sub-contractor contractual obligations of 10% should be specified in your SQ submission.
Answered
02/11/2018 12:06
38. Please could you clarify the following: Customer Filter 1 A buyer could procure an Energy Purchase Agreement - Power Purchase Agreement (level 2) for a Direct Wire Connection (level 3) But there is no Delivery Services - Electricity/Heat (level 2) for a Direct Wire Connection (would be level 3) Would an Energy Purchase Agreement - PPA include the Delivery Services of installation, operation and maintenance for a Direct Wire Connection?
CCS anticipate the Energy Purchase Agreement (EPA) and options under this heading may include services relating to the installation, operation and maintenance of the EPA. The full requirements will be specified by the customer during the Call for Competition stage.
Answered
02/11/2018 12:03
37. Section 28 in the Helga 'Read First' document makes reference to the Dun & Bradstreet score for the bidder. The Dun & Bradstreet Report does not have a single score but two scores: a Delinquency Score and a Failure Score. Which is the relevant score for the purposes of Table A set out in the Helga 'Read First' document?
CCS can confirm the Dun and Bradstreet score in the DPS Needs document relates to the D&B 'Failure' Score.
Answered
02/11/2018 11:41
36. Q.121 - Within the past three years, anywhere in the world, has the following situation applied to you or your organisation: Been involved in the preparation of the procurement procedure? Please clarify whether this question is in relation to this specific procurement procedure or any non-related procurement procedure anywhere in the world.
CCS can confirm that this question relates specifically to this procurement - RM3824 HELGA DPS.
Answered
02/11/2018 11:19
35. Page 158/169 - Q. 162 Which of the following CESG cyber certifications does your organisation currently hold? Please tick all that apply. And Q.163 Which of the following CESG cyber certifications is your organisation planning to apply for? Please tick all that apply. Please provide the evaluation criteria for these questions.
In accordance with clause 9 of the DPS Agreement, suppliers are required to have in place cyber essentials basic certification by the award of their first contract under the DPS Agreement. Please refer to the link below for further information re obtaining cyber essentials certification: https://www.cyberessentials.ncsc.gov.uk/getting-certified/ Customers will request copies of suppliers certificates prior to award of a contract under the DPS and in accordance with the obligations as set out in the DPS Agreement. If a supplier fails to provide the required certification, this may be deemed as a breach of contract and may result in a contract not being awarded. CCS can confirm the question numbers you are referencing Q.162/ Q.163 relate to the stand-alone SQ PDF (this is also available on SRS as part of the wider system), which is not applicable to RM3824. Please refer to the RM3824 Bid pack for the SQ PDF.
Answered
06/11/2018 14:12
34. Q.3 -page 3/162 - Please select the CPV (Common Procurement Vocabulary) codes which describe the product/services included in this standard Selection Questionnaire. The codes you select will help buyers to quickly understand what products/services you provide. Please clarify whether these CPV codes determine the services proposed to be provided by the suppliers or the response to Q.50 and Q.75
CCS can confirm that the CPV codes selected as part of a bidders Selection Questionnaire submission, do not determine the services to be provided by the bidder.
Answered
06/11/2018 14:10
33. Q.20 page 14/162 - Do the sub consultants mentioned in a lead bidders response have to fill in the Selection Questionnaire on the portal?
No they do not have to fill in the selection questionnaire on the portal.
Answered
30/06/2021 17:19
32. Q.179, Q.180 and Q. 181 - page 148/162 - As we do not have to answer Q150- Q154 (Past performance) - please confirm we do not have to answer these questions on documentary evidence for past performance Q.179 (List of relevant principal contracts for goods and/or services provided in the last three years), Q.180 (Certificate for each principal contract for goods and/or services in the last three years), Q.181 (Past performance information for any sub-contractor) who the supplier will rely upon to perform the contract) of the lead bidder and the supply chain.
CCS can confirm that you are not required to provide a response to the evidence request at Q.179 - Q.181.
Answered
02/11/2018 11:27
31. Q. 174, Q.175 and Q.176 page 146/162 - as we do not have to answer Q. 141, Q.142 and Q.143 (Details of insurance) - please confirm that we do not have to answer Q. 174, Q.175 and Q.176 at this stage.
CCS can confirm that you are not required to provide a response to Q.174 - Q.176, as insurance requirements are specified in Attachment 7 - Insurance Requirements, which forms part of the bid pack for the RM3824 HELGA DPS.
Answered
02/11/2018 11:28
30. Q.167 & Q. 168 page 143/162 - If I provide evidence for Q.166 (audited accounts for last 2 years) do we need to provide evidence for Q. 167 (documentary evidence for a statement of cash flow forecast for the current year) , Q.168 (bank letter outlining the current cash and credit position) , Q.169 (documentary evidence for forecast of turnover for current year) and Q.170 (statement of funding provided by the owners and/or the bank, charity accruals, accounts or an alternative means of demonstrating financial status)?
CCS can confirm that you are not required to provide a response to Q.167 - Q.170, unless you fail the Dun and Bradstreet 'Failure Scores' detailed in the DPS Needs document, point 28 (a) Table A - Financial Assessment Matrix, which forms part of the bid pack for RM3824 HELGA DPS. In the event that a bidder fails the D&B failure scores detailed as above, CCS will undertake the necessary steps in accordance with points 26 - 34 of the DPS Needs document to further assess a bidders financial status.
Answered
02/11/2018 11:29

Welcome to Supplier Registration Service chat.
Please do not send any confidential information.

Please be aware that this chat is using translation software powered by Google Translate which may affect the accuracy of the language and phrases used.

Are you sure you wish to end this chat? Are you sure you wish to disconnect this chat? New chat message from Please use the 'End Chat' link to end this chat and close the window. Do you want to reset the chat window position? Reset windows