There are 106 clarifications for this DPS
2512. The SQ keeps requesting an attachment for Q179, please confirm whether or not an answer is required for this question.
If so, please advise on the requirements for the answer in terms of the types of projects that would be deemed relevant and the documentary evidence required. Thank you
Please see section 73 in the 'Read First - RM6126 DPS Needs' document that refers to the questions that are not applicable. To confirm, Q179 is not required to be completed.
Answered
24/02/2023 14:34
2467. Our questionnaire is in the assessing stage and has been for a while. Do you know how long it usually takes in the assessing stage?
thank you.
Please raise this with the Crown Commercial Service Customer Service Centre using email address info@crowncommercial.gov.uk. Please include the name of your organisation and your SQ... reference number in the email so that your application can be traced.
Answered
30/01/2023 10:22
2429. Is it a requirement for all Suppliers under this DPS to be ISO27001 certified?
No, ISO27001 is not a requirement. There is a mandatory requirement for all suppliers to have Cyber Essentials certifications in order to be appointed. We accept ISO27001 certificate in it's place if you do not have Cyber Essentials, but it is not required as well as Cyber Essentials
Answered
12/01/2023 10:04
2289. Can you still sign up to the framework if your current Carbon Reduction Plan doesn't yet meet the criteria but are putting changes in place so it does?
Yes, we are happy to accept a draft Carbon Reduction Plan at this point as an interim measure, please share with us so we can review.
Answered
24/11/2022 11:24
2269. Hi - can you advise if an Ethical Walls Agreement can be incorporated into schedules when using the DPS?
Yes, it is possible to add in an Ethical Walls Agreement into the schedules to suit your requirement. There is an area for special terms within DPS Schedule 6 Order Form. Please ensure bidders are aware of any special terms during the procurement to adhere to transparency.
Answered
01/11/2022 10:41
2254. I have tried several times to complete the DPS questionnaire. I get a ref: SQ SWDW8H2/1 when pressing complete but when I go back to dashboard it says the questionnaire has not been completed. Therefore I cannot progress to the next stage?
It would appear that you have a technical fault with your submission. Please raise a case with Crown Commercial Service (either using the form or the telephone number both of which are on the main Crown Commercial Service web page) to raise a case, which will be passed to the relevant support team to investigate and resolve.
Answered
04/10/2022 11:19
2256. I am resubmitting our questions in case they fell through the cracks somewhere:
For DPSQ 177, to what extent are we required to write about our commitment to developing skills through internships? Are there any materials that clarify this?
For DPSQ 178, we are a small opinion polling agency with a limited supply chain (the majority of which consists of pulling respondents through online panels). How do we go about showing that our supply chain supports skills and apprenticeships in line with PPN 14/15?
These questions relate to supplementary information that may be requested from customers if/when required, the application can progress without uploading this information.
Answered
04/10/2022 11:18
2252. A) DPSQ 178 (Upload documentary evidence to demonstrate the process that ensures your supply chain supports skills, development and apprenticeships in line with PPN 14/15). We are a small opinion polling agency with a limited supply chain (the majority of which consists of pulling respondents through online panels). How do we go about showing that our supply chain supports skills and apprenticeships in line with PPN 14/15?
B) Similarly, for DPSQ 177 (Upload documentary evidence to support your commitment to developing and investing in skills, development and apprenticeships). To what extent are we required to write about our commitment to developing skills through internships? Are there any materials that clarify this?
C) Finally on DPSQ 56 (on supplying a case study that demonstrates our technical capability and capacity in delivering a research project). What is the word count limit for the case study we have to provide?
These questions relate to supplementary information that may be requested from customers if/when required, the application can progress without uploading this information.
Answered
04/10/2022 11:18
2245. please can you confirm whether question 144 is pass/fail. there are currently two clarification responses providing conflicting information; one states it is pass/fail (no.85 in the exported excel list), the other states it is not (no.16 in the exported excel list).
Question 144 is not pass/fail. We are working on getting the previous (incorrect) response updated, thank you for highlighting this.
Answered
04/10/2022 11:17
2244. Assuming we submit a fully compliant application to this DPS, how long will it take to be appointed to the DPS as a supplier? We have a potential client who is seeking to contract with us via a CCS framework and therefore need to understand whether this DPS application process will fit with the client's anticipated start date and timescales for the work to be contracted.
It totally depends on how prepared the supplier is. If they have everything they need in place and there are no issues with their financial stability, and they complete the application promptly, then it can be a matter of a week at most. Our team is very responsive to applications.
The items the suppliers would need are:
- Cyber Essentials basic certification (or ISO27001)
- Insurances: public liability, professional indemnity, employer liability
- one example of research work (a written paragraph) with a letter of confirmation signed by the contracting authority
- carbon reduction plan to adhere to the carbon net zero policy (as an interim measure, we will accept a draft) There is further information on the Carbon Reduction Plan and a template on this page).
All applications are split into the preliminary selection questionnaire and the DPSQ, suppliers can access and start their registration by following this link and scrolling down to Research & Insights and clicking on 'access as a supplier'. This will ensure they are in the right place.
On that same link, they can download the bid pack which has all the information they require. All the requirements including the examples above are defined in the DPS Needs document within the bid pack.
Answered
16/09/2022 10:55
2242. Is there an agreed inflation rate stated within the contractual documents? I cannot seem to find any mention of inflation within the core terms.
No, there is no agreed inflation rate stated within the terms and conditions. This would be something that would be addressed at call-off stage with the contracting authority. There is an area for a term on inflation to be inserted into the DPS Schedule 6 Order Form that customer's are encouraged to use.
Any questions about inflation clauses can be raised as part of the clarification period during a call-off competition.
Answered
16/09/2022 10:53
2232. Qu 104 We answered No however on review think we should have answered Yes. The assessor of our SQ has mentioned Social Value will need to be checked however there is no way of changing our answer as it has not been opened up for response. Can you confirm how we should amend this?
You can request that your application is put back into Registered 1 on the DPS platform which will allow you to amend the response to any question, including the one regarding Social Value. Then please re-submit and the team at CCS will assess and progress your application accordingly.
To be clear, we have taken your question today as the request and will put you back into Registered 1, allowing you to make the change straight away.
Answered
17/08/2022 09:45
2231. Carbon Reduction Plan - we have a published Carbon Reduction Policy with a full plan pending and likely to be available from end 2022. Can we tick yes to this question on the SQ and provide link to the policy and then provide plan in the form of the template to contracting entity?
Yes, you can tick yes and provide a link to your Carbon Reduction Policy and progress your application.
We are allowing existing policies, draft plans and/or confirmation of sign up to the Market Research Society (MRS) Carbon Net Zero Pledge in the interim whilst full plans are finalised.
We will absolutely need the reduction plan as soon as you can, but in the meantime your published Carbon Reduction Policy will be sufficient. Thank you for checking.
Answered
17/08/2022 09:45
2189. As a follow on from Qu 91 - In the SQ Evidence section, if we are able to upload audited accounts, do we need to upload the additional financial proof (turnover / P&L / cashflow)?
This is not required. Please see paragraph 73 of the DPS Needs document which lists the questions that are Not Applicable, this includes Q166 - Q172, Q176 and Q179 - Q185.
Answered
27/05/2022 15:21
2188. On the supply chain questions 65-71 (providing % figures of invoices paid within 60 days) does it include other financial obligations such as payroll?
No, this does not apply to standard regular payroll, just invoices to companies in your supply chain.
Answered
27/05/2022 15:21
2187. For several questions, we are unable to move on / receive an error message if a document is not uploaded, even if its not relevant. Should we upload a blank document in order to submit?
Yes. If any issues with the system itself you can contact the NQC support team who can help you further. You can reach them via email support@nqc.com or via phone 0161 413 7982
Answered
27/05/2022 15:20
1954. Good afternoon, there was a notification on 25.11.21 stating that a new version of Attachment 4 was amended in the Bid Pack, however, when I downloaded the bid pack there was an Attachment 5 Additional Subcontractors but last modified 28.10.21 , could you advise. Thanks
Notification
Attachment 4 amendmenta
Dear Supplier,
please be advised that a new Version of "Attachment 4 - Additional Sub-Contractor(s)" has been added to the Bid Pack to replace the previous version which contained spreadsheet drop down errors.
Regards
Crown Commercial Service
Apologies thank you for notifying us of the error, this will be rectified and we will issue a new notification to all Suppliers.
We can confirm that Additional Subcontractor information is on Attachment 5 for Research and Insights DPS.
Answered
01/04/2022 15:23
2125. Q170. -A statement of funding provided by the owners and/or the bank, charity accruals accounts or an alternative means of demonstrating financial status. I own the company 100% - what evidence do you need for this question?
This is not required. Please see paragraph 73 of the DPS Needs document which lists the questions that are Not Applicable, this includes Q170.
Answered
01/04/2022 12:01
2126. Q182. Upload documentary evidence for a statement of the turnover. What evidence do you require - this doesn't make sense to me.
This is not required. Please see paragraph 73 of the DPS Needs document which lists the questions that are Not Applicable, this includes Q182.
Answered
01/04/2022 12:01
2159. Producing a Carbon Reduction Plan - How does a virtual company with (currently) no employees and no premises go about writing a sensible carbon reduction plan? All meetings are carried out online and colleagues work from home. Many thanks
CCS are running online sessions to assist with creating a Carbon Reduction Plan, regardless of your size, to help suppliers meet compliance of procurement policy, PPN 06/21. You are able to sign up for the training, free of charge, at this link.
Alternatively, we are happy to accept instead confirmation that you are signed up to the Market Research Society's Carbon Net Zero Pledge, it costs nothing and you can access it here - https://www.mrs.org.uk/topic/sustainability-in-research
Answered
01/04/2022 12:00